How to Get Electricity to Vacant Land in Mohave County

By Johnny Lands · Updated

You have two real choices: extend a power line from the utility, or make your own electricity with solar (usually with batteries and a backup generator). Either way, there is a rule most buyers don't know until they call: Mohave County does not permit an electric service on vacant land. Power comes with your first building permit. So the order is land, then building plans, then power. Distance is the big variable for a line extension, which is why every Johnny Lands listing shows how far the nearest power is. On our listings now: No power at the lot today. The abundant sunshine makes solar a natural fit; Utility power is nearby along the area roads. The abundant sunshine makes solar a natural fit.

First, the rule nobody mentions

From the Mohave County Building Division's own FAQ: "No electric is permitted on vacant land." The first building permit you apply for is what lets the property get electric service. That might be the permit for your house, a manufactured home, or a permitted accessory building. The county will not give vacant land an address either; the address comes with the building permit too.

That doesn't mean you can't have power on your land before you build. A generator for a camping weekend or a portable solar kit for your RV is a different thing from a permanent electric service. It just means you can't call the utility the week after closing and ask for a meter on an empty lot.

Who provides power in Mohave County

UtilityWhere it servesWhat to ask for
UniSource Energy Services (UES)The Kingman and Lake Havasu areas of Mohave County, including much of the rural land around KingmanA residential new construction application and a line extension estimate for your parcel number
Mohave Electric Cooperative (MEC)Bullhead City, Fort Mohave, Mohave Valley, Golden Shores, Hualapai Mountain, Valle Vista, Peach Springs and other communitiesIts new service process and line extension terms

Service areas have edges, so don't guess. Call the utility you think serves the area, give them the parcel number (APN) or GPS coordinates from the listing, and ask them to confirm. UES customer care is at 1-877-837-4968 and MEC is at (928) 763-1100.

How a line extension works (and why distance matters so much)

When the nearest line is a few hundred feet away, the utility has to add poles or underground cable, maybe a transformer, and run it all to a meter on your property. UES's published line extension policy explains how that cost gets split:

  • The utility runs a study. UES calculates how much it will invest in your extension based on the service you need (it calls this an Incremental Contribution Study).
  • You cover the gap. If the extension costs more than the utility's allowable investment, you sign an extension agreement and pay an advance to cover the difference.
  • You can dig to save money. UES lets applicants provide the trench for service lines to its specifications, which reduces the advance.
  • Some money may come back. Extensions under that method are reviewed every year for five years to see whether a refund is owed, for example when neighbors connect to the same line.

In practice, a pole at the lot line is a very different project from a line half a mile down the road. Ask the utility for a written, itemized estimate for your exact homesite before you count on grid power. Estimates expire, so get a fresh one when you are ready to build.

How far power is on our current listings:

  • No power at the lot today. The abundant sunshine makes solar a natural fit
  • Utility power is nearby along the area roads. The abundant sunshine makes solar a natural fit
  • Power at this lot has not been confirmed yet. There are a few homes within half a mile, and the abundant sunshine makes solar a natural fit

Going solar instead

Northwest Arizona is one of the sunniest places in the country, and plenty of Mohave County homes run entirely on solar. A typical off-grid setup has four parts:

  1. Panels. Ground-mounted arrays are common on acreage because you can aim them due south without fighting a roofline.
  2. Batteries. They carry you through the night. This is usually the biggest piece of the budget.
  3. An inverter and charge controller. These turn stored power into normal household current.
  4. A backup generator. For a run of cloudy monsoon days or a heavy load like a well pump or a welder.

Size the system to how you will actually live. A weekend cabin with LED lights, a fridge and phone charging needs a small fraction of what a full-time home with air conditioning needs. Summer cooling is the big load here; shade, insulation and an evaporative cooler can shrink the system a lot.

A permanent solar system wired into a home still goes through Mohave County plan review and inspection, just like any other electrical work. Portable panels for an RV or camping are a different story.

Grid or solar: a quick comparison

Line extensionOff-grid solar
Upfront costMostly depends on distance to the nearest lineMostly depends on battery size and how much power you use
Monthly costA utility billNo bill; batteries and generator fuel over time
Air conditioningEasyPossible, but it drives the system size
TimingAfter a building permit, plus utility schedulingAfter a building permit for a permanent system
ResaleBuyers like a meter on the propertyA well-built system is a selling point for off-grid buyers

Some owners do both: they start with solar and a generator, and extend the line years later if neighbors build out toward them and the cost drops.

Before you buy: five questions to answer

  1. How far is the nearest power line or pole, and is it on my side of the road?
  2. Which utility serves this parcel? (Ask them, with the APN.)
  3. Is there a recorded utility easement to bring a line in, or would it cross a neighbor's land?
  4. Which way does the lot face? A clear southern view is worth a lot for solar.
  5. What am I building first, and when? Power follows the first building permit.

If you buy with owner financing, timing matters too: Whether you can camp or use the land for recreation while you pay depends on your land contract and local zoning — we confirm this with you before you sign. Permanent structures wait until payoff and deed recording. That gives you the payment years to collect estimates and design a solar system without rushing. Our off-grid living guide covers water and septic alongside power, and you can also read how to get water on raw land without a well.

Looking for land with power nearby? Each listing shows its distance to power. Browse Mohave County land for sale or ask us about a specific parcel.

Common questions

FAQ

Can I get electricity on vacant land in Mohave County?

Not as a permanent electric service. Mohave County does not permit electric service on vacant land; the first building permit you apply for is what allows the property to get electric. Contact the utility for availability once you are ready to build.

How much does it cost to run power to vacant land in Arizona?

It depends mostly on the distance to the nearest line, the terrain and the equipment needed. The utility decides how much it will invest and you pay an advance for the rest. Ask the utility for a written estimate for your parcel before you buy.

Who provides electricity in Kingman and Golden Valley, AZ?

UniSource Energy Services serves the Kingman and Lake Havasu areas of Mohave County. Mohave Electric Cooperative serves Bullhead City, Fort Mohave and other communities. Call the utility with your parcel number to confirm who serves your land.

Can I live off-grid with solar in Mohave County?

Yes, many homes here run on solar with batteries and a backup generator. A permanent system wired into a home goes through county plan review and inspection like other electrical work.

Do I need a permit for a generator on my land?

A portable generator for camping does not turn your land into a permitted electric service. Permanent electrical systems in a building go through the Mohave County Building Division, so ask them before you wire anything into a structure.